In this post, we will learn How to set a task as inactive without facing this issue “You can’t inactivate a task that’s in progress” in Microsoft Project.
You might also like to read Microsoft Project 2016: Any Edits made to the enterprise global template items are only available during this session
Microsoft Project: You can’t inactivate a task that’s in progress
in Microsoft Project Professional, I have tried to inactivate a task. but, I got the below error:
MS Project You can’t inactivate a task that in progress

So that I have also tried to set the Task %Complete to 100% to be Completed but, it still raises the same issue!

Cause
This issue occurs in case you are trying to set a task as inactive that is completed or still in progress.
Solution
To avoid this issue “You can’t inactivate a task that’s in progress“, you should be aware that you can only inactivate tasks that have no any progress recorded (%Complete = 0).
- You cannot inactivate completed tasks.
- Eg: %Complete = 100%
- You cannot inactivate tasks that have any progress recorded.
- Eg: %Complete > 0.
So that, you just make sure that the task is neither completed nor in progress by Setting its %Complete to 0 as shown below:

Note: To be able to set a task as inactive you should use Project Professional, The ability to inactivate tasks is not available in Project Standard.
Conclusion
In conclusion, we have learned how to set a task as inactive in Microsoft Project to avoid this issue “You can’t inactivate a task that’s in progress“.
Thank you Mohammed – quite helpful